PROJECT

Portfolio Summary As of April 2024   Total of 140 Locations
  1,116.0 MW All over Japan

Photovoltaic Power Plants 77 locations 309,335.3kW
Biomass Power Plants 2 locations 40,918.0kW
Wind Power Plants 3 locations 22,455.0kW
Hokkaido/ Tohoku
17 locations
153.0 MW
Kanto
57 locations
343.0 MW
Chubu/ Hokuriku
17 locations
56.9 MW
Kinki/Chugoku/Shikoku
29 locations
506.8 MW
Kyusyu
20 locations
56.3 MW

※1 Under-construction projects included

※2 The number is the value for the entire group

Area

Fukuoka Nougata Project

Power Plant Location Nougata-shi,
Fukuoka
Site Area 48,949㎡
Output 2.0kW 2.0MW
Work Completion Date September 2013

Nagasaki Minami Shimabara Project

Power Plant Location Minamishimabara-shi,
Nagasaki
Site Area 28,521㎡
Output 1.1kW 1.1MW
Work Completion Date August 2014

Kumamoto Nishiki Project

Power Plant Location Kuma-gun,
Kumamoto
Site Area 42,281㎡
Output 2.2kW 2.2MW
Work Completion Date February 2015

Kagoshima Ibusuki Project No. 1

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 21,830㎡
Output 1.3kW 1.3MW
Work Completion Date March 2015

Kagoshima Ibusuki Project No. 2

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 24,178㎡
Output 1.2kW 1.2MW
Work Completion Date March 2015

Kagoshima Ibusuki Project No. 3

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 13,893㎡
Output 0.9kW 0.9MW
Work Completion Date March 2015

Kumamoto Tsunagi Project

Power Plant Location Ashikita-gun,
Kumamoto
Site Area 34,482㎡
Output 1.5kW 1.5MW
Work Completion Date March 2015

Tochigi Takaku Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 9,778㎡
Output 0.9kW 0.9MW
Work Completion Date March 2015

Tochigi Toyohara Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 40,683㎡
Output 1.2kW 1.2MW
Work Completion Date March 2015

Tochigi Terako Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 39,496㎡
Output 2.4kW 2.4MW
Work Completion Date April 2015

Yamanashi Hokuto Project

Power Plant Location Hokuto-shi,
Yamanashi
Site Area 17,832㎡
Output 0.8kW 0.8MW
Work Completion Date June 2015

Saitama Kounosu Project

Power Plant Location Kounosu-shi,
Saitama
Site Area 21,213㎡
Output 1.9kW 1.9MW
Work Completion Date August 2015

Toyama Fuchu Project

Power Plant Location Toyama-shi,
Toyama
Site Area 7,421㎡
Output 0.5kW 0.5MW
Work Completion Date August 2015

Niigata Shibata Project

Power Plant Location Shibata-shi,
Niigata
Site Area 21,343㎡
Output 1.3kW 1.3MW
Work Completion Date August 2015

Fukuoka Keisen Project No.1

Power Plant Location Kaho-gun,
Fukuoka
Site Area 37,290㎡
Output 2.0kW 2.0MW
Work Completion Date September 2015

Fukuoka keisen Project No.2

Power Plant Location Kaho-gun,
Fukuoka
Site Area 27,540㎡
Output 2.0kW 2.0MW
Work Completion Date September 2015

Ibaraki Hitachiota Project

Power Plant Location Hitachiota-shi,
Ibaraki
Site Area 9,768㎡
Output 0.5kW 0.5MW
Work Completion Date September 2015

Chiba Tateyama Project

Power Plant Location Tateyama-shi,
Chiba
Site Area 7,483㎡
Output 0.5kW 0.5MW
Work Completion Date November 2015

Ibaraki Takahagi Project No.1

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 38,119㎡
Output 1.8kW 1.8MW
Work Completion Date December 2015

Ibaraki Takahagi Project No.2

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 43,336㎡
Output 2.3kW 2.3MW
Work Completion Date December 2015

Chiba Kisarazu Project

Power Plant Location Kisarazu-shi,
Chiba
Site Area 15,780㎡
Output 0.5kW 0.5MW
Work Completion Date December 2015

Aomori Tsugaru Project

Power Plant Location Tsugaru-shi,
Aomori
Site Area 62,049㎡
Output 2.4kW 2.4MW
Work Completion Date December 2015

Yamaguchi Hirao Project

Power Plant Location Kumage-gun,
Yamaguchi
Site Area 14,425㎡
Output 1.0kW 1.0MW
Work Completion Date March 2016

Okayama Tsuyama Project

Power Plant Location Tsuyama-shi,
Okayama
Site Area 2,774㎡
Output 0.3kW 0.3MW
Work Completion Date March 2016

Ibaraki Kamisu Project

Power Plant Location Kasumi-shi,
Ibaraki
Site Area 2,553㎡
Output 0.2kW 0.2MW
Work Completion Date March 2016

Shizuoka Kosai Project No.1

Power Plant Location Kosai-shi,
Shizuoka
Site Area 44,290㎡
Output 2.4kW 2.4MW
Work Completion Date March 2016

Shizuoka Kosai Project No.2

Power Plant Location Kosai-shi,
Shizuoka
Site Area 20,005㎡
Output 1.2kW 1.2MW
Work Completion Date March 2016

Saitama Honjo Project

Power Plant Location Honjo-shi,
Saitama
Site Area 12,156㎡
Output 0.8kW 0.8MW
Work Completion Date March 2016

Tochigi Manago Project

Power Plant Location Tochigi-shi,
Tochigi
Site Area 49,500㎡
Output 2.6kW 2.6MW
Work Completion Date March 2016

Fukushima Ten-ei Project

Power Plant Location Iwase-gun,
Fukushima
Site Area 132,356㎡
Output 2.3kW 2.3MW
Work Completion Date August 2016

Ibaraki Kashima Project

Power Plant Location Kashima-shi,
Ibaraki
Site Area 26,449㎡
Output 2.0kW 2.0MW
Work Completion Date September 2016

Ibaraki Namegata Project No.2

Power Plant Location Namegata-shi,
Ibaraki
Site Area 54,618㎡
Output 2.4kW 2.4MW
Work Completion Date September 2016

Ibaraki Takahagi Project No.3

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 14,874㎡
Output 0.6kW 0.6MW
Work Completion Date September 2016

Yamagata Yuza Project

Power Plant Location Akumi-gun,
Yamagata
Site Area 40,547㎡
Output 2.2kW 2.2MW
Work Completion Date September 2016

Ibaraki Kitasouma Project No.1

Power Plant Location Kitasouma-gun,
Ibaraki
Site Area 37,611㎡
Output 1.8kW 1.8MW
Work Completion Date November 2016

Ibaraki Kitasouma Project No.2

Power Plant Location Kitasouma-gun,
Ibaraki
Site Area 42,032㎡
Output 1.8kW 1.8MW
Work Completion Date November 2016

Hyogo Yumesaki Project

Power Plant Location Himeji-shi,
Hyogo
Site Area 30,743㎡
Output 2.8kW 2.8MW
Work Completion Date December 2016

Chiba Sammu Project

Power Plant Location Sammu-shi,
Chiba
Site Area 43,414㎡
Output 2.0kW 2.0MW
Work Completion Date December 2016

Ishikawa Hodatsushimizu Project

Power Plant Location Hakui-gun,
Ishikawa
Site Area 264,924㎡
Output 16.1kW 16.1MW
Work Completion Date February 2017

Oita Shuki Project

Power Plant Location Oita-shi,
Oita
Site Area 81,194㎡
Output 1.4kW 1.4MW
Work Completion Date March 2017

Tottori Daisen Project

Power Plant Location Saihaku-gun,
Tottori
Site Area 10,903㎡
Output 0.5kW 0.5MW
Work Completion Date March 2017

Hyogo Toyooka Project

Power Plant Location Toyooka-shi,
Hyogo
Site Area 76,430㎡
Output 2.6kW 2.6MW
Work Completion Date March 2017

Ibaraki Chiushida Project

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 47,158㎡
Output 2.4kW 2.4MW
Work Completion Date March 2017

Ibaraki Namegata Project No.1

Power Plant Location Namegata-shi,
Ibaraki
Site Area 36,684㎡
Output 2.8kW 2.8MW
Work Completion Date March 2017

Ibaraki Hokota Project

Power Plant Location Hokota-shi,
Ibaraki
Site Area 12,955㎡
Output 1.2kW 1.2MW
Work Completion Date March 2017

Ibaraki Yukudo Project

Power Plant Location Namegata-shi,
Ibaraki
Site Area 29,539㎡
Output 2.1kW 2.1MW
Work Completion Date March 2017

Aichi Nishio Project

Power Plant Location Nishio-shi,
Aichi
Site Area 8,024㎡
Output 0.8kW 0.8MW
Work Completion Date March 2017

Nagano Shiojiri Project

Power Plant Location Shiojiri-shi,
Nagano
Site Area 7,084㎡
Output 0.7kW 0.7MW
Work Completion Date March 2017

Miyagi Kami Project

Power Plant Location Kami-gun,
Miyagi
Site Area 18,501㎡
Output 1.2kW 1.2MW
Work Completion Date March 2017

Mie Tsu Project

Power Plant Location Tsu-shi,
Mie
Site Area 36,679㎡
Output 2.5kW 2.5MW
Work Completion Date February 2018

Aichi Mihama Project

Power Plant Location Chita-gun,
Aichi
Site Area 16,664㎡
Output 0.8kW 0.8MW
Work Completion Date February 2018

Fukushima Koriyama Project

Power Plant Location Koriyama-shi,
Fukushima
Site Area 41,853㎡
Output 1.5kW 1.5MW
Work Completion Date February 2018

Ibaraki Kamiota Project

Power Plant Location Hokota-shi,
Ibaraki
Site Area 33,998㎡
Output 2.4kW 2.4MW
Work Completion Date March 2018

Nagano Kyu-shiojiri

Power Plant Location Shiojiri-shi,
Nagano
Site Area 58,431㎡
Output 2.2kW 2.2MW
Work Completion Date March 2018

Yamaguchi Shimonoseki Project No.1

Power Plant Location Shimonoseki-shi,
Yamaguchi
Site Area 61,815㎡
Output 3.0kW 3.0MW
Work Completion Date March 2018

Yamaguchi Shimonoseki Project No.2

Power Plant Location Shimonoseki-shi,
Yamaguchi
Site Area 24,755㎡
Output 1.2kW 1.2MW
Work Completion Date March 2018

Chiba Kibara Project

Power Plant Location Sammu-shi,
Chiba
Site Area 45,142㎡
Output 1.1kW 1.1MW
Work Completion Date August 2018

Okayama Hirayama Project

Power Plant Location Okayama-shi,
Okayama
Site Area 19,387㎡
Output 1.1kW 1.1MW
Work Completion Date September 2018

Ibaraki Myoga Project

Power Plant Location Kuji-gun,
Ibaraki
Site Area 44,057㎡
Output 1.5kW 1.5MW
Work Completion Date November 2018

Hokkaido Hidaka Project

Power Plant Location Saru-gun,
Hokkaido
Site Area 46,000㎡
Output 2.7kW 2.7MW
Work Completion Date January 2019

Wakayama Kushimoto Project

Power Plant Location Higashimuro-gun,
Wakayama
Site Area 33,825㎡
Output 2.7kW 2.7MW
Work Completion Date March 2019

Kumamoto Aso Project

Power Plant Location Aso-shi,
Kumamoto
Site Area 24,766㎡
Output 1.2kW 1.2MW
Work Completion Date March 2019

Hyogo Izushi Project

Power Plant Location Toyooka-shi,
Hyogo
Site Area 21,268㎡
Output 1.5kW 1.5MW
Work Completion Date May 2019

Iwate Ichinoseki Project

Power Plant Location Ichinoseki-shi,
Iwate
Site Area 307,212㎡
Output 12.0kW 12.0MW
Work Completion Date August 2019

Nara Nakahata Project No.1

Power Plant Location Nara-shi,
Nara
Site Area 47,969㎡
Output 3.0kW 3.0MW
Work Completion Date September 2019

Nara Nakahata Project No.2

Power Plant Location Nara-shi,
Nara
Site Area 16,404㎡
Output 1.1kW 1.1MW
Work Completion Date October 2019

Hiroshima Akitakata Project

Power Plant Location Akitakata-shi,
Hiroshima
Site Area 27,461㎡
Output 1.7kW 1.7MW
Work Completion Date December 2019

Ibaraki Kunikihara Project

Power Plant Location Hitachi-shi,
Ibaraki
Site Area 362,591㎡
Output 16.0kW 16.0MW
Work Completion Date December 2019

Nagasaki Sasebo Project

Power Plant Location Sasebo-shi,
Nagasaki
Site Area 62,604㎡
Output 2.1kW 2.1MW
Work Completion Date December 2019

Nagasaki Ikeda Project

Power Plant Location Omura-shi,
Nagasaki
Site Area 25,828㎡
Output 1.9kW 1.9MW
Work Completion Date January 2020

Nagasaki Masuragahara Project

Power Plant Location Omura-shi,
Nagasaki
Site Area 24,149㎡
Output 1.3kW 1.3MW
Work Completion Date January 2020

Chiba Kimitsu Project

Power Plant Location Kimitsu-shi,
Chiba
Site Area 506,116㎡
Output 36.1kW 36.1MW
Work Completion Date March 2020

Chiba Chonan Project

Power Plant Location Chosei-gun,
Chiba
Site Area 432,776㎡
Output 24.0kW 24.0MW
Work Completion Date July 2020

Oita Usa Project

Power Plant Location Usa-shi,
Oita
Site Area 235,929㎡
Output 10.5kW 10.5MW
Work Completion Date April 2021

Chiba Kimitsu Project No.1

Power Plant Location Kimitsu-shi,
Chiba
Site Area 27,481㎡
Output 1.1kW 1.1MW
Work Completion Date January 2023

Chiba Kimitsu Project No.3

Power Plant Location Kimitsu-shi,
Chiba
Site Area 27,642㎡
Output 1.5kW 1.5MW
Work Completion Date March 2023

Chiba Sodegaura Project
【Under Construction】

Power Plant Location Sodegaura-shi,
Chiba
Site Area 69,995㎡
Output 2.2kW 2.2MW
Work Completion Date Scheduled for September 2024

Ishikawa Monzen Project(Wind Power)
【Under Construction】

Power Plant Location Wajima-shi,
Ishikawa
Site Area 7,448㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025

Ishikawa Akasumi Project(Wind Power)
【In Preparation】

Power Plant Location Hakui-gun,
Ishikawa
Site Area 65,492㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025

Ishikawa Yada Project(Wind Power)
【In Preparation】

Power Plant Location Hakui-gun,
Ishikawa
Site Area 40,111㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025

Fukuoka Nougata Project

Power Plant Location Nougata-shi,
Fukuoka
Site Area 48,949㎡
Output 2.0kW 2.0MW
Work Completion Date September 2013

Nagasaki Minami Shimabara Project

Power Plant Location Minamishimabara-shi,
Nagasaki
Site Area 28,521㎡
Output 1.1kW 1.1MW
Work Completion Date August 2014

Kumamoto Nishiki Project

Power Plant Location Kuma-gun,
Kumamoto
Site Area 42,281㎡
Output 2.2kW 2.2MW
Work Completion Date February 2015

Kagoshima Ibusuki Project No. 1

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 21,830㎡
Output 1.3kW 1.3MW
Work Completion Date March 2015

Kagoshima Ibusuki Project No. 2

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 24,178㎡
Output 1.2kW 1.2MW
Work Completion Date March 2015

Kagoshima Ibusuki Project No. 3

Power Plant Location Ibusuki-shi,
Kagoshima
Site Area 13,893㎡
Output 0.9kW 0.9MW
Work Completion Date March 2015

Kumamoto Tsunagi Project

Power Plant Location Ashikita-gun,
Kumamoto
Site Area 34,482㎡
Output 1.5kW 1.5MW
Work Completion Date March 2015

Tochigi Takaku Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 9,778㎡
Output 0.9kW 0.9MW
Work Completion Date March 2015

Tochigi Toyohara Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 40,683㎡
Output 1.2kW 1.2MW
Work Completion Date March 2015

Tochigi Terako Project

Power Plant Location Nasu-gun,
Tochigi
Site Area 39,496㎡
Output 2.4kW 2.4MW
Work Completion Date April 2015

Yamanashi Hokuto Project

Power Plant Location Hokuto-shi,
Yamanashi
Site Area 17,832㎡
Output 0.8kW 0.8MW
Work Completion Date June 2015

Saitama Kounosu Project

Power Plant Location Kounosu-shi,
Saitama
Site Area 21,213㎡
Output 1.9kW 1.9MW
Work Completion Date August 2015

Toyama Fuchu Project

Power Plant Location Toyama-shi,
Toyama
Site Area 7,421㎡
Output 0.5kW 0.5MW
Work Completion Date August 2015

Niigata Shibata Project

Power Plant Location Shibata-shi,
Niigata
Site Area 21,343㎡
Output 1.3kW 1.3MW
Work Completion Date August 2015

Fukuoka Keisen Project No.1

Power Plant Location Kaho-gun,
Fukuoka
Site Area 37,290㎡
Output 2.0kW 2.0MW
Work Completion Date September 2015

Fukuoka keisen Project No.2

Power Plant Location Kaho-gun,
Fukuoka
Site Area 27,540㎡
Output 2.0kW 2.0MW
Work Completion Date September 2015

Ibaraki Hitachiota Project

Power Plant Location Hitachiota-shi,
Ibaraki
Site Area 9,768㎡
Output 0.5kW 0.5MW
Work Completion Date September 2015

Chiba Tateyama Project

Power Plant Location Tateyama-shi,
Chiba
Site Area 7,483㎡
Output 0.5kW 0.5MW
Work Completion Date November 2015

Ibaraki Takahagi Project No.1

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 38,119㎡
Output 1.8kW 1.8MW
Work Completion Date December 2015

Ibaraki Takahagi Project No.2

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 43,336㎡
Output 2.3kW 2.3MW
Work Completion Date December 2015

Chiba Kisarazu Project

Power Plant Location Kisarazu-shi,
Chiba
Site Area 15,780㎡
Output 0.5kW 0.5MW
Work Completion Date December 2015

Aomori Tsugaru Project

Power Plant Location Tsugaru-shi,
Aomori
Site Area 62,049㎡
Output 2.4kW 2.4MW
Work Completion Date December 2015

Yamaguchi Hirao Project

Power Plant Location Kumage-gun,
Yamaguchi
Site Area 14,425㎡
Output 1.0kW 1.0MW
Work Completion Date March 2016

Okayama Tsuyama Project

Power Plant Location Tsuyama-shi,
Okayama
Site Area 2,774㎡
Output 0.3kW 0.3MW
Work Completion Date March 2016

Ibaraki Kamisu Project

Power Plant Location Kasumi-shi,
Ibaraki
Site Area 2,553㎡
Output 0.2kW 0.2MW
Work Completion Date March 2016

Shizuoka Kosai Project No.1

Power Plant Location Kosai-shi,
Shizuoka
Site Area 44,290㎡
Output 2.4kW 2.4MW
Work Completion Date March 2016

Shizuoka Kosai Project No.2

Power Plant Location Kosai-shi,
Shizuoka
Site Area 20,005㎡
Output 1.2kW 1.2MW
Work Completion Date March 2016

Saitama Honjo Project

Power Plant Location Honjo-shi,
Saitama
Site Area 12,156㎡
Output 0.8kW 0.8MW
Work Completion Date March 2016

Tochigi Manago Project

Power Plant Location Tochigi-shi,
Tochigi
Site Area 49,500㎡
Output 2.6kW 2.6MW
Work Completion Date March 2016

Fukushima Ten-ei Project

Power Plant Location Iwase-gun,
Fukushima
Site Area 132,356㎡
Output 2.3kW 2.3MW
Work Completion Date August 2016

Ibaraki Kashima Project

Power Plant Location Kashima-shi,
Ibaraki
Site Area 26,449㎡
Output 2.0kW 2.0MW
Work Completion Date September 2016

Ibaraki Namegata Project No.2

Power Plant Location Namegata-shi,
Ibaraki
Site Area 54,618㎡
Output 2.4kW 2.4MW
Work Completion Date September 2016

Ibaraki Takahagi Project No.3

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 14,874㎡
Output 0.6kW 0.6MW
Work Completion Date September 2016

Yamagata Yuza Project

Power Plant Location Akumi-gun,
Yamagata
Site Area 40,547㎡
Output 2.2kW 2.2MW
Work Completion Date September 2016

Ibaraki Kitasouma Project No.1

Power Plant Location Kitasouma-gun,
Ibaraki
Site Area 37,611㎡
Output 1.8kW 1.8MW
Work Completion Date November 2016

Ibaraki Kitasouma Project No.2

Power Plant Location Kitasouma-gun,
Ibaraki
Site Area 42,032㎡
Output 1.8kW 1.8MW
Work Completion Date November 2016

Hyogo Yumesaki Project

Power Plant Location Himeji-shi,
Hyogo
Site Area 30,743㎡
Output 2.8kW 2.8MW
Work Completion Date December 2016

Chiba Sammu Project

Power Plant Location Sammu-shi,
Chiba
Site Area 43,414㎡
Output 2.0kW 2.0MW
Work Completion Date December 2016

Ishikawa Hodatsushimizu Project

Power Plant Location Hakui-gun,
Ishikawa
Site Area 264,924㎡
Output 16.1kW 16.1MW
Work Completion Date February 2017

Oita Shuki Project

Power Plant Location Oita-shi,
Oita
Site Area 81,194㎡
Output 1.4kW 1.4MW
Work Completion Date March 2017

Tottori Daisen Project

Power Plant Location Saihaku-gun,
Tottori
Site Area 10,903㎡
Output 0.5kW 0.5MW
Work Completion Date March 2017

Hyogo Toyooka Project

Power Plant Location Toyooka-shi,
Hyogo
Site Area 76,430㎡
Output 2.6kW 2.6MW
Work Completion Date March 2017

Ibaraki Chiushida Project

Power Plant Location Takahagi-shi,
Ibaraki
Site Area 47,158㎡
Output 2.4kW 2.4MW
Work Completion Date March 2017

Ibaraki Namegata Project No.1

Power Plant Location Namegata-shi,
Ibaraki
Site Area 36,684㎡
Output 2.8kW 2.8MW
Work Completion Date March 2017

Ibaraki Hokota Project

Power Plant Location Hokota-shi,
Ibaraki
Site Area 12,955㎡
Output 1.2kW 1.2MW
Work Completion Date March 2017

Ibaraki Yukudo Project

Power Plant Location Namegata-shi,
Ibaraki
Site Area 29,539㎡
Output 2.1kW 2.1MW
Work Completion Date March 2017

Aichi Nishio Project

Power Plant Location Nishio-shi,
Aichi
Site Area 8,024㎡
Output 0.8kW 0.8MW
Work Completion Date March 2017

Nagano Shiojiri Project

Power Plant Location Shiojiri-shi,
Nagano
Site Area 7,084㎡
Output 0.7kW 0.7MW
Work Completion Date March 2017

Miyagi Kami Project

Power Plant Location Kami-gun,
Miyagi
Site Area 18,501㎡
Output 1.2kW 1.2MW
Work Completion Date March 2017

Mie Tsu Project

Power Plant Location Tsu-shi,
Mie
Site Area 36,679㎡
Output 2.5kW 2.5MW
Work Completion Date February 2018

Aichi Mihama Project

Power Plant Location Chita-gun,
Aichi
Site Area 16,664㎡
Output 0.8kW 0.8MW
Work Completion Date February 2018

Fukushima Koriyama Project

Power Plant Location Koriyama-shi,
Fukushima
Site Area 41,853㎡
Output 1.5kW 1.5MW
Work Completion Date February 2018

Ibaraki Kamiota Project

Power Plant Location Hokota-shi,
Ibaraki
Site Area 33,998㎡
Output 2.4kW 2.4MW
Work Completion Date March 2018

Nagano Kyu-shiojiri

Power Plant Location Shiojiri-shi,
Nagano
Site Area 58,431㎡
Output 2.2kW 2.2MW
Work Completion Date March 2018

Yamaguchi Shimonoseki Project No.1

Power Plant Location Shimonoseki-shi,
Yamaguchi
Site Area 61,815㎡
Output 3.0kW 3.0MW
Work Completion Date March 2018

Yamaguchi Shimonoseki Project No.2

Power Plant Location Shimonoseki-shi,
Yamaguchi
Site Area 24,755㎡
Output 1.2kW 1.2MW
Work Completion Date March 2018

Chiba Kibara Project

Power Plant Location Sammu-shi,
Chiba
Site Area 45,142㎡
Output 1.1kW 1.1MW
Work Completion Date August 2018

Okayama Hirayama Project

Power Plant Location Okayama-shi,
Okayama
Site Area 19,387㎡
Output 1.1kW 1.1MW
Work Completion Date September 2018

Ibaraki Myoga Project

Power Plant Location Kuji-gun,
Ibaraki
Site Area 44,057㎡
Output 1.5kW 1.5MW
Work Completion Date November 2018

Hokkaido Hidaka Project

Power Plant Location Saru-gun,
Hokkaido
Site Area 46,000㎡
Output 2.7kW 2.7MW
Work Completion Date January 2019

Wakayama Kushimoto Project

Power Plant Location Higashimuro-gun,
Wakayama
Site Area 33,825㎡
Output 2.7kW 2.7MW
Work Completion Date March 2019

Kumamoto Aso Project

Power Plant Location Aso-shi,
Kumamoto
Site Area 24,766㎡
Output 1.2kW 1.2MW
Work Completion Date March 2019

Hyogo Izushi Project

Power Plant Location Toyooka-shi,
Hyogo
Site Area 21,268㎡
Output 1.5kW 1.5MW
Work Completion Date May 2019

Iwate Ichinoseki Project

Power Plant Location Ichinoseki-shi,
Iwate
Site Area 307,212㎡
Output 12.0kW 12.0MW
Work Completion Date August 2019

Nara Nakahata Project No.1

Power Plant Location Nara-shi,
Nara
Site Area 47,969㎡
Output 3.0kW 3.0MW
Work Completion Date September 2019

Nara Nakahata Project No.2

Power Plant Location Nara-shi,
Nara
Site Area 16,404㎡
Output 1.1kW 1.1MW
Work Completion Date October 2019

Hiroshima Akitakata Project

Power Plant Location Akitakata-shi,
Hiroshima
Site Area 27,461㎡
Output 1.7kW 1.7MW
Work Completion Date December 2019

Ibaraki Kunikihara Project

Power Plant Location Hitachi-shi,
Ibaraki
Site Area 362,591㎡
Output 16.0kW 16.0MW
Work Completion Date December 2019

Nagasaki Sasebo Project

Power Plant Location Sasebo-shi,
Nagasaki
Site Area 62,604㎡
Output 2.1kW 2.1MW
Work Completion Date December 2019

Nagasaki Ikeda Project

Power Plant Location Omura-shi,
Nagasaki
Site Area 25,828㎡
Output 1.9kW 1.9MW
Work Completion Date January 2020

Nagasaki Masuragahara Project

Power Plant Location Omura-shi,
Nagasaki
Site Area 24,149㎡
Output 1.3kW 1.3MW
Work Completion Date January 2020

Chiba Kimitsu Project

Power Plant Location Kimitsu-shi,
Chiba
Site Area 506,116㎡
Output 36.1kW 36.1MW
Work Completion Date March 2020

Chiba Chonan Project

Power Plant Location Chosei-gun,
Chiba
Site Area 432,776㎡
Output 24.0kW 24.0MW
Work Completion Date July 2020

Oita Usa Project

Power Plant Location Usa-shi,
Oita
Site Area 235,929㎡
Output 10.5kW 10.5MW
Work Completion Date April 2021

Chiba Kimitsu Project No.1

Power Plant Location Kimitsu-shi,
Chiba
Site Area 27,481㎡
Output 1.1kW 1.1MW
Work Completion Date January 2023

Chiba Kimitsu Project No.3

Power Plant Location Kimitsu-shi,
Chiba
Site Area 27,642㎡
Output 1.5kW 1.5MW
Work Completion Date March 2023

Chiba Sodegaura Project
【Under Construction】

Power Plant Location Sodegaura-shi,
Chiba
Site Area 69,995㎡
Output 2.2kW 2.2MW
Work Completion Date Scheduled for September 2024

Ishikawa Monzen Project(Wind Power)
【Under Construction】

Power Plant Location Wajima-shi,
Ishikawa
Site Area 7,448㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025

Ishikawa Akasumi Project(Wind Power)
【In Preparation】

Power Plant Location Hakui-gun,
Ishikawa
Site Area 65,492㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025

Ishikawa Yada Project(Wind Power)
【In Preparation】

Power Plant Location Hakui-gun,
Ishikawa
Site Area 40,111㎡
Output 7.5kW 7.5MW
Work Completion Date Scheduled for June 2025